Evaluation of Construction Project’s Cost Using BIM Technology

Evaluation of Construction Project’s Cost Using BIM Technology

Ruwaida Al-Musawi* Sepanta Naimi

Faculty of Engineering-Architecture, Department of Civil Engineering, Altınbaş Üniversitesi, Bağcılar 34217, İstanbul, Turkey

Corresponding Author Email: 
203724096@ogr.altinbas.edu.tr
Page: 
469-476
|
DOI: 
https://doi.org/10.18280/mmep.100212
Received: 
10 September 2022
|
Revised: 
13 November 2022
|
Accepted: 
20 November 2022
|
Available online: 
28 April 2023
| Citation

© 2023 IIETA. This article is published by IIETA and is licensed under the CC BY 4.0 license (http://creativecommons.org/licenses/by/4.0/).

OPEN ACCESS

Abstract: 

In this research, a case study is explored and examined by choosing a construction project. The budget of this project is calculated and analyzed using two methods. A comparison between these two approaches is conducted in terms of performance, effort, accuracy, and cost of calculation. These two techniques are manual quantity surveying and numerical project take-off depending on BIM technology (REVIT software package). The quantity take-off of steel, concrete, and other vital architectural elements and structural building components was considered. The results of this work revealed that there are perfect agreements between the traditional cost-estimation method and the ANSYS numerical calculation associated with all construction elements and components, indicating that BIM technology can offer a reliable solution to determine the construction project cost with higher complexity and components. Furthermore, it was found that the use of REVIT software has cut a significant number of human errors that occurred during the estimation process and quantity take-off for the project cost. In addition, the results of the manual and numerical methods of cost calculation indicated that the REVIT software had saved much time and effort needed for engineers to estimate the budget related to this challenging case study that represents a hospital building with various structural components.

Keywords: 

cost estimation, BIM technology, construction project, quantity surveying, REVIT software, budget management

1. Introduction

Due to the rising number of small-, medium-, and large-scale construction projects worldwide, and because of the increasing rates of projects’ complexity, the estimation process of the budget related to the construction project has become more complicated, effort, and time-consuming, and may contribute to a larger number of human errors [1-4]. The motivation of this research is reflected in the critical benefits, and substantial contributions of modern constriction techniques like Building Information Modeling (BIM) in helping civil engineers, quantity surveyors, designers, and planners calculate the volume of construction materials with higher degrees of accuracy, less human errors, less effort, and very low amount of time and cost required to make the materials quantity take-off. BIM technology is vital because conventional approaches to materials quantity take-off consume much time, effort, and budget to make the quantity take-off. Furthermore, traditional quantity take-off techniques implemented by engineers may contribute to several numbers of errors. Thus, these conventional methods may not be effective, reliable, or more precise in evaluating the required construction materials.

The construction projects’ activities and parameters associated with each building task have been growing in the last decades, leading to higher challenges and difficulties for quantity surveyors to calculate the cost of each project as the complexity of these projects is remarkable. Additionally, if the calculation process relies on human efforts, the cost assessment will contribute to various errors and less precision, and it will consume much time [5-7]. In this context, designers, planners, and scholars have been working through decades of Research and Development (R&D) to develop BIM technology and REVIT software package that can be capable of providing state-of-the-art cost-evaluation techniques by which these problems can be alleviated and resolved. Besides, planners and project managers improved the BIM software potential to enable flexible and practical evaluation of the budget of large-scale construction projects characterized by a significant level of complexity and linked to a considerable number of tasks and activities. In this project, the BIM technology is implemented to calculate the budget of a construction project relying on the REVIT software, one of the novel software programs which can implement BIM principles in the project’s cost-evaluation process. Shaqour [8] executed research examining the beneficial impacts and critical role of BIM technology implementation on the construction industry in Egypt. They applied quantitative, analytical, and descriptive methods to achieve the study goal. They reported that the Egyptian construction industry faces some challenges mirrored by losses in construction materials, budget, and execution time. The quantitative, analytical, and descriptive analysis (which covered 106 Egyptian experts in BIM technology) revealed that applying BIM technology is greatly beneficial for the Egyptian construction sector and can significantly improve the project management procedure throughout the project’s lifetime. Charef et al. [9] carried out research exploring the major advantages and key characteristics of BIM technology in the construction industry. They selected a case study (presenting a veterinary clinic) using the REVIT/ Auto-Desk software package. They implemented 5D BIM modelling through which a three-dimensional configuration of the veterinary clinic was executed, besides cost and time estimation. Their BIM analysis of their case study revealed that applying BIM principles with 5D contributed to significant accuracy in evaluating the budget and schedule of the veterinary clinic. Also, it was found that using BIM technology can replace manual calculation approaches for construction projects’ time and cost, saving much effort and reducing human errors. In addition, results indicated that the design process could be effectively automated, making BIM modelling greatly beneficial for construction project performance. Banihashemi et al. [10] conducted an analysis examining the critical role of BIM technology modelling in facilitating construction projects’ execution and improving performance. They integrated machine learning (ML) principles into the BIM system. They also developed a prototype to train the ML algorithms in estimating the construction project’s cost with fewer errors. The software that operated these ML algorithms with 5D-BIM modelling was MATLAB software. Their numerical analysis revealed that using 5D modelling of BIM technology and integrating ML algorithms into the estimation process contributed to significant improvements in evaluating the construction project’s budget. Also, numerical results confirmed that BIM technology implementation with ML algorithms provided higher accuracy and eliminated human errors. Sepasgozar et al. [2] carried out research investigating the critical role of BIM technology in evaluating the construction project’s cost. They applied critical content and systematic reviews through which BIM technology’s contribution and substantial role in estimating construction projects cost were identified. Their critical literature analysis revealed that implementing BIM technology, particularly 5D modelling, has several significant advantages to the construction project. Results indicated that 5D modelling helps engineers and surveyors estimate the construction project budget with a higher accuracy degree and minimizes human errors, as manual calculation methods can be avoided. Lin [11] carried out a study identifying major BIM technology roles and critical contributions to the construction project in estimating safety index and productivity. Lin depended on a case study analysis of Singapore’s safety system and intelligent productivity framework. Also, they followed a comprehensive literature review. Several recent articles and academic publications addressed the importance of critical BIM technology significance in accomplishing higher safety standards and productivity of construction projects. The comprehensive literature analysis revealed that BIM technology plays a beneficial role and positively impacts the construction industry in achieving considerable safety standards. Also, BIM technology can improve construction projects’ productivity rate and manage their resources. Mahamood and Fathi [12] executed an analysis examining the important role of BIM principles in managing and designing a seismic building associated with Malaysian governmental construction projects. They depended on a semi-structured qualitative approach through which interviews were conducted with construction industry experts and stakeholders from the Malaysian government to address the critical role of BIM technology in seismic building design. Their qualitative research approach revealed that BIM technology plays a significant role in managing, designing, and monitoring buildings with earthquakes and seismic impacts. Also, BIM modelling can help control project activities and improve construction projects’ performance. Quoc et al. [13] performed research investigating the significance of BIM technology adoption and implementation in improving the performance of several construction projects. They applied a cross-sectional descriptive quantitative study through which questionnaire surveys were applied, covering 159 experts in the BIM technology used in the construction sector. Their cross-sectional research findings indicated that implementing BIM technology in the construction industry provides advantageous impacts and positive effects for facility managers, contractors, owners, structural and architectural engineers, and other construction stakeholders. Also, the results revealed that BIM technology contributed to several significant improvements in the design drawings’ quality. In addition, BIM technology offered a remarkable reduction in the changes/ conflicts/ claims throughout the project execution. Moreover, BIM implementation helped offer flexible planning and resource management and mobilization. Also, utilizing BIM principles contributed to a considerable reduction in human errors and time savings in estimating the construction project’s cost and time. Further, Heigermoser et al. [14], Alizadehsalehi et al. [15], Arif et al. [16], Toan et al. [17], Jia [18], Xu et al. [19], Adekunle et al. [20] carried out research examining the critical benefits of BIM technology and REVIT software in managing construction. They found that using the REVIT software and BIM principles could help increase the performance of project execution, accuracy in making quantity take-off, and reduce human errors.

The structure of this work consists of some topics that will be covered in the following sections. For instance, section two will discuss the materials, methods, and significant research approaches adopted and executed to carry out the primary data collection of this work. Following this section, section three describes the preliminary research results obtained from the research approaches implemented by the researcher. Section four illustrates the research discussions by relating the finding of this work to other researchers. Section five depicts the conclusions and a summary of the main research outcomes of this study.

2. Materials and Methods

2.1 Case study description

Figure 1. The case study: Hospital building

The case study consists of a hospital building comprising four floors (ground floor, first floor, second floor, and roof). The major hospital building’s rooms include the main entrance, optical, pharmacy, secondary entrance, lobby, health gas system, electrical board room, main reception, waiting, special waiting, doctor room, general examination, special examination, cafeteria, prayer, garden, special corridor, nursing, patient room, locker, change clothes, doctors break, patient sterilization room, medical sterilization room, sterile corridor, operations hall, Lasik operation, kitchenette, UBS room, and elevator room (see Table 1). Figure 1 presents a concrete-based model of the hospital building.

In addition, Figures 2, 3, and 4 represent the shop drawing related to the floor plan of the ground, first, second, and roof floors.

Figure 2. The ground floor of the hospital construction project

Table 1. Some details on the hospital construction building

#

Floor

Area (m2)

Parts of the floor, use

1

Ground floor

600

The main entrance, Optical, Pharmacy, Secondary entrance, Lobby, Healthy gas system, Electrical Room, Main Reception, Waiting, Special Waiting, Doctor room, General Examination, Special Examination, Cafeteria, Prayer, Laboratory, Garden, Special corridor, Nursing, Inpatient room.

2

First floor

600

Locker, Change Clothes, Doctors Break, Patient sterilization room, Medical sterilization room, Sterile corridor, Operations hall, Lasik Operation, Kitchenette, UBS Room.

3

Second floor

600

Locker, Change Clothes, Doctors Break, Patient sterilization room, Medical sterilization room, Sterile corridor, Operations hall, Lasik Operation, Kitchenette, UBS Room.

4

Roof floor

41.65

Elevator rooms.

Figure 3. The first and second floors plan of the hospital construction project

Figure 4. The roof plan of the hospital construction project

2.2 Manual quantity surveying procedure

2.2.1 Concrete evaluation

Table 2 presents the process of calculating the cut.

Table 2. Calculating the cut manually

Cut (m3) = Excavation area × Excavation depth

Value

Cut = 24.2 × 25.2 × 2.00

1,219.73 m3

Table 3 presents the process of calculating the blinding volume.

Table 3. Calculating the blinding volume manually

Blinding (m3) (100 mm depth)

Value

Volume = (L1×L2×H) – opening volume

54.40 m3

Volume = (24.2×25.2×0.1) – (4.8×13.7×0.1)

Table 4 presents the process of calculating the boulder volume.

Table 4. Calculating the boulder volume manually

Boulder Volume (m3) (200 mm depth)

Value

Volume = (L1×L2×H) – opening volume

108.82 m3

Volume = (24.2×25.2×0.2) – (4.8×13.7×0.2)

L1, L2, and H in Table 4 depict the length, width, and height of the cube related to the concrete boulder, respectively.

Table 5. Calculating the sub-base volume manually

Sub-base Volume (m3) (400 mm depth)

Value

Volume = (L1×L2×H) – opening volume

217.64 m3

Volume = (24.2×25.2×0.4) – (4.8×13.7×0.4)

Table 5 represents the process of calculating the boulder volume.

Table 6. Calculating the lean concrete volume manually

Lean concrete Volume (m3) (100 mm depth)

Value

Volume = (L1×L2×H) – opening volume

54.40 m3

Volume = (24.2×25.2×0.1) – (4.8×13.7×0.1)

Table 6 describes the process of calculating the lean concrete volume.

Table 7. Calculating the bitumen volume manually

Bitumen Volume (m3) (8 mm depth)

Value

Volume = (L1×L2×H) – opening volume

4.35 m3

Volume = (24.2×25.2*0.008) – (4.8×13.7×0.008)

Table 7 illustrates the process of calculating the bitumen volume.

Table 8. Calculating the reinforced concrete volume for the raft foundation

Item

Slab Length (m)

Slab Width (m)

Depth (m)

Opening Volume (Cuboid Hole) (m3)

Value

Raft Foundation

24.00

25.00

0.65

(4.8×13.7×0.65) = 42.74

347m3

Table 8 illustrates the calculation procedure for the reinforced concrete volume for the raft foundation.

The process of calculation conducted in Table 8 can be expressed in the following formula:

Reinforced Concrete (m3) = (length × width × depth of foundation) – opening volume           (1)

Hence, the reinforced concrete volume equals:

24 × 25 × 0.65 - (4.8 × 13.7 × 0.65) = 347.3 m3.

Table 9. Calculating the reinforced concrete columns’ volume

Concrete Columns Volume = Length × Width × Height

Total height from raft footing to second floor = (5 + 4 + 4 + 0.65) m, = 13.65 m

Total height from raft footing to second floor = (5 + 4 + 4 + 4+ 0.65) m, = 17.65 m, without Slabs height

Item

length

width

height

#

Total

C1

0.75

0.30

13.65

10

30.72

C1

0.75

0.30

17.65

1

3.97

C2

0.75

0.30

17.65

1

3.97

C2

0.75

0.30

13.65

10

30.72

C3

0.75

0.30

17.65

1

3.97

C3

0.75

0.30

13.65

3

9.21

C4

0.75

0.35

13.65

1

3.58

C5

0.45

0.45

13.65

4

11.06

C6

0.70

0.25

13.65

4

9.56

Total columns reinforced concrete

106.8 m3

Table 9 illustrates the calculation for the reinforced concrete columns’ volume.

Table 10. Calculating the reinforced concrete walls’ volume

Total height from raft footing to second floor = (5 + 4 + 4 +4+ 0.65) m = 17.65 m, without Slabs height

Reinforced concrete walls = Length × Width × Height

Item

Length (m)

Width (m)

Height (m)

Total (m3)

SW1 & SW2

8.10

0.30

17.65

42.89

Elevator 1 & 2

18.8

0.25

17.65

82.96

Total Walls reinforced Concrete Volume

125.85 m3

Table 10 describes the estimation of the volume of the reinforced concrete walls.

Table 11. Calculating the reinforced concrete beams’ volume

Beams Concrete = Height × Width × Length

Item

Length (m)

Width (m)

Height (m)

#

Total (m3)

B1

98.00

0.35

0.70

3

72.03

B2

51.68

0.70

0.32

3

34.73

B3

42.80

0.8

0.32

3

32.87

B4

16.3

0.5

0.32

3

7.82

B6

17.43

0.35

0.7

3

12.81

B7

26.56

0.35

0.8

3

22.31

Total of beams reinforced concrete

182.6 m3

Table 11 describes the estimation of the volume of the reinforced concrete beams.

Table 12. Calculating the volume of the hollow/waffle blocks

Hollow/Waffle Blocks Volume = Number of blocks × Volume of one block × Number of floors

Value

volume= #Blocks×0.0192

140.04 m3

Volume = 2431 × 0.0192 × 3

Table 12 describes the estimation of the volume of the hollow/waffle blocks.

Table 13 describes the estimation of the reinforced concrete slabs’ volume.

Table 14 describes the estimation of the total reinforced concrete volume.

Table 13. Calculating reinforced concrete slabs’ volume

Slabs reinforced Concrete Volume = (Total Volume of one slab – (Hollow Blocks Volume +

Beams reinforced Concrete Volume + opening volume)) × Number of floors

Item

Floor total volume

one floor (m3)

Floor opening

one floor (m3)

Beams concrete

one floor (m3)

Hollow blocks volume

one floor (m3)

#

Total (m3)

Slab on grade 1

34.38 m2 × 0.18 m = 6.19

---

-----

----

1

6.19

Slab on grade 2

492.77 m2 × 0.36 m = 177.40

----

----

----

1

177.40

GF, 1st, 2nd floor

600 m2 × 0.32 m = 192

96.37 m2 × 0.32 m = 30.84

182.57 / 3 = 60.86

140.04 /3 = 46.68

3

160.86

Top of roof Solid slab

41.65 m2 × 0.15 m = 6.25

----

----

----

1

6.25

Steps

66 steps × 0.5 × 0.3 m × 0.165 m × 1 m = 1.63

----

----

0.36

1

1.63

Stair ladders

34 m × 1 m × 0.3 m = 10.2

----

----

15.84

1

10.2

Total of reinforced concrete slabs

362.53

Table 14. Calculating total reinforced concrete volume

Raft foundation

Columns

Walls

Beams

Slabs

347.26 m3

106.76 m3

125.85 m3

182.57 m3

362.53 m3

Total = 1,124.97 m3

2.2.2 Steel evaluation

According to International Building Code (IBC) and National Concrete Masonry Association (NCMA), the recommended steel reinforcement ratio in concrete amounts between 0.5% and 4% [21]. Furthermore, the building code ACI 318-19 determines the minimum longitudinal reinforcement ratio for the column with a ratio of 0.01 times the concrete column’s gross area. The reinforcement steel is computed using the formula:

Reinforcement Steel (kg)=Bar weight (kg/m)×Length (m) × No. of bars,               (2)

where, bar weight can be estimated by the expression:

Bar Weight $(\mathrm{kg} / \mathrm{m})=\operatorname{Diameter}^2\left(\mathrm{~mm}^2\right) / 162$,           (3)

Table 15. The classification of steel diameters and weight used in this project

Dia. used in this project

Weight /m = Dia. (mm2)/162

Total weight (kg/m)

25 mm

(25)2/162

3.8

20 mm

(20)2/162

2.47

18 mm

(18)2/162

2.00

16 mm

(16)2/162

1.580

14 mm

(14)2/162

1.21

12 mm

(12)2/162

0.89

10 mm

(10)2/162

0.62

The classification of steel diameters and weight used in this project are explained in Table 15.

Table 16. The overall steel calculation manually

Part

Weight (kg)

Raft foundation steel reinforcement

25950.88

Columns steel reinforcement

39699.8

Walls steel reinforcement

24534.7

Slabs steel reinforcement

41504.9

Beams steel reinforcement

31335.20

Total steel reinforcement in this project (kg)

163025.5

Total = 163.0255 Ton

The overall steel calculation is explained in Table 16.

2.2.3 Architectural elements evaluation

Table 17. The quantity calculation of external blocks manually

Blocks Number = ((L×H) – (opening area))×(1.00)/(Area of Blocks)

Floor

Length

(m)

Height

(m)

Opening area (m2)

Area of Block (m2)

Total

GR

74.86

5.00

79.25

0.08

3688

1st

74.86

4.00

----

0.08

3743

2nd

74.86

4.00

----

0.08

3743

Roof

74.86

1.00

----

0.08

936

Total blocks

12110

968.8 m2

The quantity calculation of external blocks is explained in Table 17.

Table 18. The quantity calculation of the external glass wall manually

Floor

Length (m)

Height (m)

Total area (m2)

GR

15.01

5.00

75.05

1st

-----

----

-----

2nd

-----

----

-----

Roof

-----

----

-----

Total Area (m2)

75.05 m2

The quantity calculation of the external glass wall is illustrated in Table 18.

Table 19. The quantity calculation of external plaster manually

Plaster Area = ((L*H) – (Opening area))

Floor

Length (m)

Height (m)

Opening area (m2)

Total area (m2)

GR/ 1st / 2nd and Roof

98.00

15.79

79.25

1468.17

Plaster Area (m2)

1468.17 m2

The quantity calculation of external plaster is illustrated in Table 19.

Table 20. The quantity calculation of external stone manually

Stones Area = ((L*H) – (Opening area))

Floor

Length (m)

Height (m)

Opening area (m2)

Total area (m2)

GR/ 1st / 2nd and Roof

98.00

15.79

79.25

1468.17

Stones area m2

1468.17 m2

The quantity calculation of external stone is illustrated in Table 20.

Table 21. The quantity calculation of internal blocks manually

Blocks Number = ((L*H) – (opening area))×(1.0)/Area of Blocks

Floor

Length (m)

Height (m)

Opening Area (m2)

Area of Block (m2)

Total

GR

114.25

5.00

46.50

0.08

6560

1st

162.56

4.00

68.5

0.08

7272

2nd

162.56

4.00

68.5

0.08

7272

Roof

----

----

----

----

----

Total Blocks

21,104

1688.32 m2

The quantity calculation of internal blocks is illustrated in Table 21.

Table 22. The quantity calculation of the internal glass wall manually

Floor

Length (m)

Height (m)

Total area (m2)

GR

44.35

5.00

221.75

1st

27.32

4.00

109.28

2nd

27.32

4.00

109.28

Roof

----

----

----

Total Area (m2)

440.31 m2

The quantity calculation of the internal glass wall is depicted in Table 22.

Table 23. The quantity calculation of the internal plaster and paint manually

Internal plaster and paint = ((L*H) – (opening area))

Floor

Length (m)

Height (m)

Opening area (m2)

Total area (m2)

GR

324.72

5.00

168.58

1455.02

1st

433.12

4.00

154.49

1577.99

2nd

162.56

4.00

154.49

1577.99

Roof

----

----

----

----

Total Area

4611 m2

The quantity calculation of the internal plaster and paint is depicted in Table 23.

Table 24. The quantity calculation of the internal tiles manually

Floor

Area

GR

407.04

1st

462.13

2nd

462.13

Roof

492.47

Total area of tiles

1823.77 m2

The quantity calculation of the internal tiles is depicted in Table 24.

2.3 Revit quantity surveying procedure

Table 25. The total concrete quantity calculated using the REVIT software

Raft foundation

Columns

Walls

Beams

Slabs

349.59 m3

106.37 m3

126.48 m3

183.79 m3

364.01 m3

Total = 1130.24 m3

The total concrete quantity calculated using the REVIT software is presented in Table 25.

Table 26. The total steel reinforcement estimated using the REVIT software

Part

Weight (kg)

Raft foundation steel reinforcement

26566.05

Columns steel reinforcement

40123.40

Walls steel reinforcement

24936.53

Slabs steel reinforcement

40523.30

Beams steel reinforcement

30671.84

Total steel reinforcement in this project (kg)

162821.12

162.82112 Ton

The total steel reinforcement estimated using the REVIT software is presented in Table 26.

The total quantity of the project’s architectural components is computed using REVIT in Table 27.

Also, the internal tiles area was evaluated using the REVIT software, which is described in Table 28.

Table 27. The total quantity of the project’s architectural components using the REVIT software

Category

Quantity

External Blocks

1036.48 m2

External Glass Wall Area

72.93 m2

External Plaster

1570.68 m2

External Stones

1690.59 m2

Internal Blocks

1868.96 m2

Internal Glass Wall Area

494.69 m2

Internal Plaster and Paint

4869.58 m2

Table 28. The quantity survey of the project’s internal tiles using the REVIT software

Floor

Area

GR

413.36

1st

473.29

2rd

473.29

Roof

513.97

Total area of tiles (m2)

1873.91 m2

3. Results

Based on the manual and numerical calculation processes of the construction project cost of this case study (hospital building), a comparison between the manual cost estimation approach and the REVIT software computation related to concrete and steel quantity take-off can be presented in Table 29.

Table 29. A comparison between the manual cost estimation approach and the REVIT software computation related to concrete and steel quantity take-off

Comparison

Manual results

REVIT results

Error percent

Concrete (m3)

Blinding

54.40

55.12

0.51%

Raft concrete

347.26

349.59

0.67%

Slabs concrete

362.53

364.01

0.41%

Columns concrete

106.76

106.37

0.37%

Beams concrete

182.57

183.79

0.67%

Walls

125.85

126.48

0.50%

Steel (kg)

Raft steel

25950.88

26566.05

2.37%

Slabs steel

41504.90

40523.3

2.37%

Columns steel

39699.80

40123.4

1.07%

Beams steel

31335.20

30671.84

2.12%

Walls steel

24534.70

24936.53

1.64%

Table 30. A comparison between the manual cost estimation technique and the REVIT software computation process related to architectural elements quantity take-off

Comparison

Manual results

Revit results

Cut (m3)

1219.73

1222.58

External Blocks (m2)

968.8

1036.48

Internal Blocks (m2)

1688.32

1868.96

External plaster (m2)

1468.17

1570.68

Internal plaster and paint (m2)

4611

4869.58

Stones (m2)

1468.17

1690.59

Floor Tiles (m2)

1823.77

1873.91

Internal Glass (m2)

440.31

494.69

External Glass (m2)

75.05

72.93

Also, another comparison between the manual cost estimation technique and the REVIT software computation process related to architectural elements quantity take-off can be presented in Table 30.

It can be inferred from the two tables that there are excellent agreements between the conventional cost-estimation method and the ANSYS numerical calculation associated with all construction elements and components, indicating that BIM technology can offer a reliable solution to determine the construction project cost with higher complexity and components. In addition, the use of REVIT software has cut a significant number of human errors that occurred during the estimation process and quantity take-off for the project cost. Furthermore, the REVIT software has saved much time and effort needed for engineers to estimate the budget related to this challenging case study that represents a hospital building with various structural components.

4. Discussion

This research revealed that there are excellent agreements between the conventional cost-estimation method and the ANSYS numerical calculation associated with estimating the quantity of reinforcement steel, reinforcement concrete, and architectural elements. These results indicate that employing BIM technology is beneficial in providing a reliable solution to locate the construction project cost with higher levels of complexity and components. The results also indicated that using REVIT software had reduced a significant number of human errors throughout the quantity take-off of the project’s cost. The research findings also confirmed that the REVIT software could minimize much effort and time required by engineers to assess the budget related to challenging construction projects with higher complexity and components, like this case study. The results of this work are consistent with the research findings of [1-4], who stated that BIM technology and the REVIT software tool could minimize much of human errors and achieve a higher degree of precision. Also, these results are consistent with the findings of [5-7], who reported that the REVIT program could save considerable effort and time that would be significantly consumed by engineers to estimate the construction project cost. Also, the results of this study are compatible with [8-10], who analyzed the critical role of the BIM technology and REVIT software in estimating project costs and found that using the REVIT program can significantly cut effort, time, and cost required to calculate the construction projects costs that have higher complexity. Also, they found that employing BIM technology could enhance cost-calculation accuracy.

5. Conclusions

In this study, a case study is explored and examined, representing a construction project of a hospital building. The budget of this building is calculated and analyzed using two techniques. A comparison between these two approaches is conducted according to performance, effort, accuracy, and cost of calculation. These two approaches include manual quantity surveying and numerical project take-off, which depends on BIM technology using the REVIT software package. The quantity take-off of steel, concrete, and other vital architectural elements and structural building components was considered. The results of this work revealed the following aspects:

1- There are excellent agreements between the conventional cost-estimation method and the ANSYS numerical calculation associated with all construction elements and components, indicating that BIM technology can offer a reliable solution to determine the construction project cost with higher complexity and components.

2- The use of REVIT software has cut a significant number of human errors that occurred during the estimation process and quantity take-off for the project cost.

3- The REVIT software has saved much time and effort needed for engineers to estimate the budget related to this challenging case study that represents a hospital building with various structural components.

  References

[1] San Cristóbal, J.R., Carral, L., Diaz, E., Fraguela, J.A., Iglesias, G. (2018). Complexity and project management: A general overview. Complexity, 2018: 4891286. https://doi.org/10.1155/2018/4891286

[2] Sepasgozar, S.M., Costin, A.M., Karimi, R., Shirowzhan, S., Abbasian, E., Li, J. (2022). BIM and digital tools for state-of-the-art construction cost management. Buildings, 12(4): 396. https://doi.org/10.3390/buildings12040396

[3] Villaschi, F.S., Carvalho, J.P., Bragança, L. (2022). BIM-based method for the verification of building code compliance. Applied System Innovation, 5(4): 64. https://doi.org/10.3390/asi5040064

[4] Zhan, Z., Tang, Y., Wang, C., Yap, J.B.H., Lim, Y.S. (2022). System dynamics outlook on BIM and lean interaction in construction quantity surveying. Iranian Journal of Science and Technology, Transactions of Civil Engineering, 46: 3947-3962. https://doi.org/10.1007/s40996-022-00833-w

[5] Moragane, H.P.M.N.L.B., Perera, B.A.K.S., Palihakkara, A.D. (2022). Application of computer vision for construction progress monitoring. In Proceedings the 10th World Construction Symposium, p. 126. https://doi.org/10.31705/WCS.2022.11

[6] Nguyen, T.Q., Lou, E.C., Nguyen, B.N. (2022). A theoretical BIM-based framework for quantity take-off to facilitate progress payments: the case of high-rise building projects in Vietnam. International Journal of Building Pathology and Adaptation. https://doi.org/10.1108/IJBPA-10-2021-0139

[7] Wu, Z., Ma, G. (2022). Automatic generation of BIM-based construction schedule: Combining an ontology constraint rule and a genetic algorithm. Engineering, Construction and Architectural Management. https://doi.org/10.1108/ECAM-12-2021-1105

[8] Shaqour, E.N. (2022). The role of implementing BIM applications in enhancing project management knowledge areas in Egypt. Ain Shams Engineering Journal, 13(1): 101509. https://doi.org/10.1016/j.asej.2021.05.023

[9] Charef, R., Alaka, H., Emmitt, S. (2018). Beyond the third dimension of BIM: A systematic review of literature and assessment of professional views. Journal of Building Engineering, 19: 242-257. https://doi.org/10.1016/j.jobe.2018.04.028

[10] Banihashemi, S., Khalili, S., Sheikhkhoshkar, M., Fazeli, A. (2022). Machine learning-integrated 5D BIM informatics: building materials costs data classification and prototype development. Innovative Infrastructure Solutions, 7(3): 1-25. https://doi.org/10.1007/s41062-022-00822-y

[11] Lin, E.T.A. (2022). An intelligent system for determining productivity and safety index using building information modelling: A case study of IPASS in Singapore. In Research Companion to Building Information Modelling. Edward Elgar Publishing: 415-435. https://doi.org/10.4337/9781839105524.00031

[12] Mahamood, S.Z.H., Fathi, M.S. (2022). Seismic building design work process using building information modelling (BIM) technology for Malaysian Government projects. International Journal of Disaster Resilience in the Built Environment, 13(2): 211-232. https://doi.org/10.1108/IJDRBE-10-2021-0135

[13] Quoc, T.N., Van, T.N., Ngoc, D.T., Xuan, A.P. (2022). Adoption of building information modelling in the construction project life cycle: Benefits for stakeholders. Architecture and Engineering, 7(1): 56-71. https://doi.org/10.23968/2500-0055-2022-7-1-56-71

[14] Heigermoser, D., de Soto, B.G., Abbott, E.L.S., Chua, D.K.H. (2019). BIM-based last planner system tool for improving construction project management. Automation in Construction, 104: 246-254. https://doi.org/10.1016/j.autcon.2019.03.019

[15] Alizadehsalehi, S., Hadavi, A., Huang, J.C. (2020). From BIM to extended reality in AEC industry. Automation in Construction, 116: 103254. https://doi.org/10.1016/j.autcon.2020.103254

[16] Arif, M.S., Nasihien, R.D., Sutowijoyo, H. (2021). BIM implementation in mall laves project construction Surabaya. International Journal of Engineering, Science and Information Technology, 1(2): 13-15. https://doi.org/10.52088/ijesty.v1i2.49

[17] Toan, N.Q., Anh, P.X., Tam, N.V. (2023). Trends in BIM tools adoption in construction project implementation: A case study in Vietnam. In Proceedings of FORM 2022, pp. 9-19. https://doi.org/10.1007/978-3-031-10853-2_2

[18] Jia, Y. (2021). Application analysis of BIM technology in project management. In 2021 International Conference on Intelligent Transportation, Big Data & Smart City (ICITBS), pp. 55-58. https://10.1109/ICITBS53129.2021.00022

[19] Xu, J., Li, B.K., Luo, S.M. (2018). Practice and exploration on teaching reform of engineering project management course in universities based on BIM simulation technology. EURASIA Journal of Mathematics, Science and Technology Education, 14(5): 1827-1835. https://doi.org/10.29333/ejmste/85417

[20] Adekunle, S.A., Aigbavboa, C.O., Ejohwomu, O.A. (2022). Understanding the BIM actor role: A study of employer and employee preference and availability in the construction industry. Engineering, Construction and Architectural Management. https://doi.org/10.1108/ECAM-08-2021-0714

[21] National Concrete Masonry Association (NCMA). (2022). TEK 12-04D, Steel Reinforcement for Concrete Masonry. Available at: https://ncma.org/resource/steel-reinforcement-for-concrete-masonry/, accessed on November 2, 2022.